PacifiCorp-PIS096
199.9 MW storage in Lake, OR · In queue since November 2024 · Proposed COD December 2028
199.9 MW
Capacity
1
Components
Battery
2 years
In Queue
In Progress (unknown study)
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-31
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
Entered PacifiCorp interconnection queue
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available with proposed COD of 2028-12-31. No independent sources to validate or contradict this date.
Developer: LBNL lists PacifiCorp as developer. This is the utility itself, not a shell LLC, suggesting utility-owned storage. No external sources to confirm or provide additional context.
Status: LBNL status is 'active' with IA 'In Progress (unknown study)'. Queue entry is recent (Nov 2024), consistent with early-stage development.
About
Generated Apr 10, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
PacifiCorp-PIS096 is a proposed energy storage project located in Lake County, Oregon. The development project, with a total capacity of 199.9 MW, consists entirely of battery storage. PacifiCorp is both the developer and the utility for the project.
The project is currently active in the PacifiCorp interconnection queue, with an entry date of November 27, 2024. The proposed commercial operation date is December 31, 2028. The interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Summer Lake substation.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
OR
County
Lake
Grid Region
Mountain West
Market
—
Developer
PacifiCorp
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
NRIS/ERIS
Point of Interconnection
Summer Lake substation
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Oregon in Oregon growth signals — PPAs, construction, new projects
Summary analysis with parallel narrative sections and visualizations.
OR Solar 3, LLC
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Berkshire Power
Data-driven briefing on Berkshire Hathaway — fleet, generation, financial, and news signals.
Berkshire Wind Power Project
Data-driven briefing on Berkshire Hathaway — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.