PacifiCorp-PIS095
19.9 MW generation in Jefferson, OR · In queue since November 2024 · Proposed COD December 2027
19.9 MW
Capacity
1
Components
Solar
1y 8m
In Queue
In Progress (unknown study)
IA Phase
COD target: 2027
Total Duration
3y 1m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
PacifiCorp-PIS095 is a proposed solar generation project located in Jefferson County, Oregon, with a total capacity of 19.9 MW. The project, being developed by PacifiCorp, is interconnected to the Cove substation. It is currently listed as active in the PacifiCorp interconnection queue (PIS), with a queue entry date of November 27, 2024, and a proposed commercial operation date of December 31, 2027. The interconnection agreement status is listed as "In Progress (unknown study)".
The proposed project consists solely of solar generation, with the 19.9 MW capacity attributed to this technology. PacifiCorp is listed as both the utility and the entity associated with the project. The project is located in the West region.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
OR
County
Jefferson
Grid Region
Mountain West
Market
—
Developer
PacifiCorp
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
NRIS/ERIS
Point of Interconnection
Cove substation
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project PacifiCorp-PIS095Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.