PacifiCorp-PIS091
17 MW generation in Salt Lake, UT · In queue since October 2024 · Proposed COD January 2026
17 MW
Capacity
1
Components
Gas
1y 9m
In Queue
In Progress (unknown study)
IA Phase
COD target: 2026
Total Duration
1y 3m
Schedule
6 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-01-01
PacifiCorp-PIS091 is a proposed 17 MW gas-fired generation project located in Salt Lake County, Utah. The development project, sponsored by PacifiCorp, consists of a single 17 MW gas component. It is interconnected to the grid at the Gadsby substation.
The project is currently active in the PacifiCorp interconnection queue as of its entry date of October 31, 2024. The proposed commercial operation date is January 1, 2026, and the interconnection agreement status is listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
UT
County
Salt Lake
Grid Region
Mountain West
Market
—
Developer
PacifiCorp
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
NRIS/ERIS
Point of Interconnection
Gadsby substation
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project PacifiCorp-PIS091Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.