PacifiCorp-PIS089
400 MW generation in Lincoln, WY · In queue since October 2024 · Proposed COD October 2028
400 MW
Capacity
1
Components
Wind
1y 9m
In Queue
In Progress (unknown study)
IA Phase
COD target: 2028
Total Duration
4 years
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-10-01
PacifiCorp-PIS089 is a proposed 400 MW wind generation project located in Lincoln County, Wyoming. The project is listed in the PacifiCorp interconnection queue with an entry date of October 31, 2024. Its proposed commercial operation date is October 1, 2028.
The interconnection agreement for PacifiCorp-PIS089 is currently listed as "In Progress (unknown study)". The point of interconnection is the Naughton-Ben Lomond #2 transmission line. The project has appeared in recent news coverage regarding PacifiCorp's generation development plans.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
WY
County
Lincoln
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
ERIS
Point of Interconnection
Naughton-Ben Lomond #2 transmission line
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project PacifiCorp-PIS089Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.