PacifiCorp-PIS025
199 MW storage in Utah, UT · In queue since July 2022 · Proposed COD September 2025
199 MW
Capacity
1
Components
Battery
4 years
In Queue
In Progress (unknown study)
IA Phase
COD target: 2025
Total Duration
3y 2m
Schedule
10 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-09-01
PacifiCorp-PIS025 is a proposed 199 MW battery storage project located in Utah County, Utah. The project, being developed by PacifiCorp, consists of a 199 MW battery energy storage system. It is currently active in the PacifiCorp interconnection queue (queue entry date of July 16, 2022) with a proposed commercial operation date of September 1, 2025. The interconnection agreement is currently listed as "In Progress (unknown study)". The point of interconnection is the Mercer substation.
The project is located in the western region of the United States. Recent news coverage has discussed PacifiCorp's plans for energy storage projects in Utah, but it is unknown if this specific project was mentioned.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
UT
County
Utah
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
ERIS
Point of Interconnection
Mercer substation
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project PacifiCorp-PIS025Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.