PacifiCorp-C2-45
600 MW hybrid in Power, ID · In queue since April 2022 · Proposed COD October 2030
600 MW
Capacity
1
Components
Solar
4y 3m
In Queue
IA Executed
IA Phase
COD target: 2030
Total Duration
8y 6m
Study Phase
Cluster 2
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2030-10-01
Interconnection Agreement executed per LBNL queue status
PacifiCorp-C2-45 is a proposed 600 MW hybrid solar and battery project located in Power County, Idaho. The development project consists of 600 MW of solar generation. It is listed as active in the PacifiCorp interconnection queue, with an entry date of April 28, 2022, and a proposed commercial operation date of December 31, 2025. The point of interconnection is the Borah substation.
The project is being developed by PacifiCorp. It has appeared in recent news coverage regarding PacifiCorp's renewable energy development plans.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
ID
County
Power
Grid Region
Mountain West
Market
—
Developer
NextEra Energy Resources Interconnection Holdings, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
ERIS
Point of Interconnection
Borah substation
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Top solar plant owners in the US
Data tables and metrics from the InfraSure database.
Top solar plant owners in the US
Data tables and metrics from the InfraSure database.
Top 10 solar states
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.