PacifiCorp-C2-28
199 MW storage in Salt Lake, UT · In queue since April 2022 · Proposed COD February 2031
199 MW
Capacity
1
Components
Battery
4y 3m
In Queue
IA Executed
IA Phase
COD target: 2031
Total Duration
8y 10m
Study Phase
Cluster 2
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2031-02-06
Interconnection Agreement executed per LBNL queue status
PacifiCorp-C2-28 is a proposed 199 MW battery storage project located in Salt Lake County, Utah. The project, under development by Dominguez Grid, LLC, consists entirely of battery storage. It is interconnected to the PacifiCorp grid at the Terminal substation.
The project is listed in the PacifiCorp interconnection queue as entry C2-28, with an original queue entry date of April 18, 2022. The proposed commercial operation date is July 1, 2024, and the Interconnection Agreement (IA) has been executed.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
UT
County
Salt Lake
Grid Region
Mountain West
Market
—
Developer
Dominguez Grid, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
NRIS
Point of Interconnection
Terminal substation
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.