PacifiCorp-C2-209
20 MW storage in Uintah, UT · In queue since May 2022 · Proposed COD November 2026
20 MW
Capacity
1
Components
Battery
4y 2m
In Queue
Suspended
IA Phase
COD target: 2026
Total Duration
4y 6m
Study Phase
Cluster 2
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-11-30
PacifiCorp-C2-209 is a proposed 20 MW battery storage project located in Uintah County, Utah. The project, under development by Revolve Vernal BESS, LLC, consists of a 20 MW battery energy storage system. It is interconnected to the PacifiCorp grid at the Ashley substation.
The project is currently active in the PacifiCorp interconnection queue, with an interconnection request date of May 15, 2022, and a proposed commercial operation date of October 1, 2025. The interconnection agreement for the project has been executed.
Generated from interconnection queue and public data sources
Realization risk through commissioning — schedule slippage, construction cost overrun, and COD probability vs the stated window. The diligence view that determines whether the project comes online when promised. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
UT
County
Uintah
Grid Region
Mountain West
Market
—
Developer
Revolve Vernal BESS, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
ERIS
Point of Interconnection
Ashley substation
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with curtailment risk decomposed by congestion zone and ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, first-year DSCR, and construction cost overrun exposure — what determines whether the deal clears its covenants once online. Projected across price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project PacifiCorp-C2-209Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.