PacifiCorp-C2-178
199 MW storage in Crook, OR · In queue since May 2022 · Proposed COD December 2032
199 MW
Capacity
1
Components
Battery
4y 6m
In Queue
IA Executed
IA Phase
COD target: 2032
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
10y 7m
Study Phase
Cluster 2
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2032-12-31
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
Interconnection Agreement executed per LBNL queue status
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available with proposed COD of 2032-12-31. No independent news or research sources found to validate or contradict this date.
Developer: Only LBNL filing entity 'Oathkeeper Storage, LLC' is available. No news sources found to identify parent company or operating entity behind this project LLC.
Status: LBNL shows 'active' status with IA Executed. No news coverage found to provide ground-truth updates on construction or development progress.
About
Generated Apr 10, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
PacifiCorp-C2-178 is a proposed 199 MW battery storage project located in Crook County, Oregon. The project, developed by PacifiCorp, is currently active in the PacifiCorp interconnection queue as of May 15, 2022, with a proposed commercial operation date of December 31, 2028. The point of interconnection is the Corral substation.
The project consists entirely of battery storage, with a total capacity of 199 MW. There is no information available regarding an interconnection agreement or news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
OR
County
Crook
Grid Region
Mountain West
Market
—
Developer
Oathkeeper Storage, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
ERIS
Point of Interconnection
Corral substation
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Oregon in Oregon growth signals — PPAs, construction, new projects
Summary analysis with parallel narrative sections and visualizations.
OR Solar 3, LLC
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
FPL Energy Vansycle LLC (OR)
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Wal-Mart Truth or Consequences PV
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.