PacifiCorp-C2-07
80 MW hybrid in Crook, OR · In queue since April 2022 · Proposed COD December 2036
80 MW
Capacity
1
Components
Solar
4y 3m
In Queue
IA Executed
IA Phase
COD target: 2036
Total Duration
14y 8m
Study Phase
Cluster 2
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2036-12-31
PacifiCorp-C2-07 is a proposed 80 MW hybrid solar and battery project located in Crook County, Oregon. The development project consists of 80 MW of solar capacity. It is listed in the PacifiCorp interconnection queue as of April 1, 2022, with a proposed commercial operation date of May 30, 2026. The point of interconnection is the Baldwin Road-Ponderosa transmission line.
The project is currently listed as active in the interconnection queue. No developer is specified in the queue data. No information is available regarding an interconnection agreement or news coverage.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
OR
County
Crook
Grid Region
Mountain West
Market
—
Developer
Three Springs Interconnection D LLC
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
NRIS
Point of Interconnection
Baldwin Road-Ponderosa transmission line
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project PacifiCorp-C2-07Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.