PacifiCorp-C2-04
199.9 MW storage in Klamath, OR · In queue since April 2022 · Proposed COD December 2026
199.9 MW
Capacity
1
Components
Battery
4y 1m
In Queue
Facility Study
IA Status
COD target: 2026
Total Duration
4y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-15
Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
PacifiCorp-C2-04 is a proposed 199.9 MW battery storage project located in Klamath County, Oregon. The project, being developed by PacifiCorp, is interconnected to the PacifiCorp system at the Snow Goose substation. It entered the interconnection queue on April 1, 2022, with a proposed commercial operation date of December 15, 2026. The project's interconnection status is currently in the Facility Study phase.
The proposed project has been the subject of recent news coverage related to regulatory matters.
Generated from interconnection queue and public data sources
State
OR
County
Klamath
Grid Region
Mountain West
Market
—
Developer
PacifiCorp
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
—
Point of Interconnection
Snow Goose substation
Data Source
LBNL
Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesNo Ask reports yet for this entity.
Ask about Project PacifiCorp-C2-04Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.