Project PacifiCorp-C2-04 — Project Summary

Queue ID
PacifiCorp-C2-04
Capacity
199.9 MW
Technology
Battery
Status
active
Location
Klamath, OR
Region
West
Developer
PacifiCorp
IA Status
Facility Study

PacifiCorp-C2-04

PacifiCorp-C2-04BetaActiveBatteryPacifiCorpLBNL

199.9 MW storage in Klamath, OR · In queue since April 2022 · Proposed COD December 2026

BA: BPATNERC: WECCRC: RCW

199.9 MW

Capacity

1

Components

Battery

4y 1m

In Queue

Facility Study

IA Status

COD target: 2026

Interconnection

Total Duration

4y 8m

Facilities Study50%
Queue EntryApr 1, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-15

Risk Analytics

Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability
Counterparty exposure
About

PacifiCorp-C2-04 is a proposed 199.9 MW battery storage project located in Klamath County, Oregon. The project, being developed by PacifiCorp, is interconnected to the PacifiCorp system at the Snow Goose substation. It entered the interconnection queue on April 1, 2022, with a proposed commercial operation date of December 15, 2026. The project's interconnection status is currently in the Facility Study phase.

The proposed project has been the subject of recent news coverage related to regulatory matters.

Generated from interconnection queue and public data sources

Project Details

State

OR

County

Klamath

Grid Region

Mountain West

Market

Developer

PacifiCorp

Utility

PacifiCorp

Entity

PacifiCorp

Service Type

Point of Interconnection

Snow Goose substation

Data Source

LBNL

ApplicantPacifiCorpRTO Insider · 2025-08-28
AgencyOregon Public Utility CommissionRTO Insider · 2025-08-28
RulingApprovalRTO Insider · 2025-08-28
Generation Forecast

Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year horizon (through 2034)
P10 / P50 / P90 confidence bands
Weather + policy + demand scenarios
Financial Forecast

Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year cashflow horizon
P10 / P50 / P90 DSCR bands
Price + demand + policy scenarios
Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
MID-C
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

News & Articles (2)Beta

Last updated 2026-03-26