PacifiCorp-C1-15
2.3 MW storage in Klamath, OR · In queue since May 2021 · Proposed COD July 2024
2.3 MW
Capacity
1
Components
Battery
5y 6m
In Queue
IA Executed
IA Phase
COD target: 2024
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 2m
Schedule
28 months past proposed COD
Study Phase
Cluster 1
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2024-07-26
About
Generated Apr 10, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
PacifiCorp-C1-15 is a proposed 2.3 MW battery storage project located in Klamath County, Oregon. The project, developed by PacifiCorp, consists of a single 2.3 MW battery component.
The project is in the PacifiCorp interconnection queue with an entry date of May 5, 2021, and a proposed commercial operation date of February 1, 2023. The interconnection agreement for the project has been executed. The point of interconnection is Circuit 5L49 out of Lakeport substation.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
OR
County
Klamath
Grid Region
Mountain West
Market
—
Developer
PacifiCorp
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
ERIS
Point of Interconnection
Circuit 5L49 out of Lakeport substation
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Oregon in Oregon growth signals — PPAs, construction, new projects
Summary analysis with parallel narrative sections and visualizations.
OR Solar 3, LLC
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Berkshire Power
Data-driven briefing on Berkshire Hathaway — fleet, generation, financial, and news signals.
Berkshire Wind Power Project
Data-driven briefing on Berkshire Hathaway — fleet, generation, financial, and news signals.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.