PacifiCorp-C1-14
120 MW hybrid in Emery, UT · In queue since April 2021 · Proposed COD February 2029
120 MW
Capacity
1
Components
Solar
5y 3m
In Queue
Suspended
IA Phase
COD target: 2029
Total Duration
7y 10m
Study Phase
Cluster 1
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-02-27
PacifiCorp-C1-14 is a proposed 120 MW hybrid solar and battery project located in Emery County, Utah. The development project consists of 120 MW of solar capacity. It is listed in the PacifiCorp interconnection queue as of April 21, 2021, with a proposed commercial operation date of November 30, 2024.
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the Emery-Sigurd #2 transmission line.
Generated from interconnection queue and public data sources
Realization risk through commissioning — schedule slippage, construction cost overrun, and COD probability vs the stated window. The diligence view that determines whether the project comes online when promised. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
UT
County
Emery
Grid Region
Mountain West
Market
—
Developer
Muddy Creek Energy, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
ERIS
Point of Interconnection
Emery-Sigurd #2 transmission line
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with curtailment risk decomposed by congestion zone and ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, first-year DSCR, and construction cost overrun exposure — what determines whether the deal clears its covenants once online. Projected across price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project PacifiCorp-C1-14Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.