PacifiCorp-C012
750 MW generation in Wheatland, MT · In queue since July 2020 · Proposed COD October 2023
750 MW
Capacity
1
Components
Wind
6 years
In Queue
—
IA Status
COD target: 2023
Total Duration
3y 3m
Schedule
33 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-10-31
PacifiCorp-C012 is a proposed 750 MW wind generation project located in Wheatland County, Montana. The project, developed by PacifiCorp, consists of 750 MW of wind capacity. It is listed as active in the PacifiCorp interconnection queue as of July 31, 2020, with a proposed commercial operation date of October 31, 2023. The point of interconnection is the Loco Mountain substation.
The development project is located in the Western region of the United States. It has appeared in recent news coverage regarding PacifiCorp's generation development plans.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
MT
County
Wheatland
Grid Region
Mountain West
Market
—
Developer
—
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
ERIS
Point of Interconnection
Loco Mountain substation
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project PacifiCorp-C012Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.