PacifiCorp-907
80 MW hybrid in Klamath, OR · In queue since July 2017 · Proposed COD October 2030
80 MW
Capacity
1
Components
Solar
9 years
In Queue
IA Executed
IA Phase
Signed Mar 2020
Queue → IA
2y 8m
IA → COD
10y 7m
Total Duration
2y 8m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2030-10-04
PacifiCorp-907 is a proposed 80 MW hybrid solar and battery project located in Klamath County, Oregon. The project, developed by Fresh Air Energy II, LLC, consists of 80 MW of solar generation. It is interconnected to the PacifiCorp system at the Klamath Falls-Lone Pine transmission line.
The project is in the PacifiCorp interconnection queue as PacifiCorp-907, with an entry date of July 12, 2017. The proposed commercial operation date was December 1, 2019, and the Interconnection Agreement has been executed. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
OR
County
Klamath
Grid Region
Mountain West
Market
—
Developer
Fresh Air Energy II, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
ERIS
Point of Interconnection
Klamath Falls-Lone Pine transmission line
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project PacifiCorp-907Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.