PacifiCorp-838
525 MW hybrid in Utah, UT · In queue since December 2016 · Proposed COD September 2025
525 MW
Capacity
1
Components
Solar
9y 7m
In Queue
IA Executed
IA Phase
Signed Mar 2023
Queue → IA
6y 3m
IA → COD
2y 6m
Total Duration
6y 3m
Schedule
10 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2025-09-15
Interconnection Agreement executed with PacifiCorp
PacifiCorp-838 is a proposed 525 MW hybrid solar and battery project located in Utah County, Utah. The development project, under the name PacifiCorp-838, is being developed by Faraday Interconnection LLC. It consists of 525 MW of solar capacity.
The project is in the PacifiCorp interconnection queue, with an original queue entry date of December 8, 2016, and a proposed commercial operation date of December 1, 2018. The interconnection agreement (IA) has been executed. The point of interconnection is the Clover-Oquirrh transmission line.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
UT
County
Utah
Grid Region
Mountain West
Market
—
Developer
Faraday Interconnection LLC
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
NRIS
Point of Interconnection
Clover-Oquirrh transmission line
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Top solar plant owners in the US
Data tables and metrics from the InfraSure database.
Top solar plant owners in the US
Data tables and metrics from the InfraSure database.
Top 10 solar states
Data tables and metrics from the InfraSure database.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.