Project PacifiCorp-838 — Project Summary

Queue ID
PacifiCorp-838
Capacity
525 MW
Technology
Solar+Battery
Status
active
Location
Utah, UT
Region
West
Developer
Faraday Interconnection LLC
IA Status
IA Executed

PacifiCorp-838

PacifiCorp-838BetaActiveSolarBatteryPacifiCorpLBNL

525 MW hybrid in Utah, UT · In queue since December 2016 · Proposed COD September 2025

BA: PACENERC: WECCRC: RCW

525 MW

Capacity

1

Components

Solar

9y 7m

In Queue

IA Executed

IA Phase

Signed Mar 2023

Interconnection

Queue → IA

6y 3m

IA → COD

2y 6m

Total Duration

6y 3m

Schedule

10 months past proposed COD

Construction75%
Queue EntryDec 8, 2016

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection AgreementMar 3, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2025-09-15

Cross-source intelligence
Beta
Low confidence·0 sources·as of 2026-06-01
Expected COD
2025-09-15
From queue filing
Developer
Faraday Interconnection LLC
From queue filing
Status
Active
Active — IA executed March 2023, 525 MW solar+battery project in Utah County targeting Q3 2025 COD
Financing
Unannounced
Key milestones
IA executedMar 3, 2023Most recent

Interconnection Agreement executed with PacifiCorp

About

PacifiCorp-838 is a proposed 525 MW hybrid solar and battery project located in Utah County, Utah. The development project, under the name PacifiCorp-838, is being developed by Faraday Interconnection LLC. It consists of 525 MW of solar capacity.

The project is in the PacifiCorp interconnection queue, with an original queue entry date of December 8, 2016, and a proposed commercial operation date of December 1, 2018. The interconnection agreement (IA) has been executed. The point of interconnection is the Clover-Oquirrh transmission line.

Generated from interconnection queue and public data sources

Development Risk

Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Financing close probability
EPC + tax-equity counterparty
Project Details

State

UT

County

Utah

Grid Region

Mountain West

Market

Developer

Faraday Interconnection LLC

Utility

PacifiCorp

Entity

PacifiCorp

Service Type

NRIS

Point of Interconnection

Clover-Oquirrh transmission line

Data Source

LBNL

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

10-year P50 forecast
First-year output estimate
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

10-year revenue projection
First-year DSCR
Financing close risk
Market Context
Approximate
ISO / RTO
MOUNTAIN_WEST
Trading Hub
FOURCORNERS
Hub Confidence
UNKNOWN

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.