PacifiCorp-836
400 MW generation in Carbon, WY · In queue since December 2016 · Proposed COD December 2027
400 MW
Capacity
1
Components
Wind
9y 7m
In Queue
IA Executed
IA Phase
Signed Mar 2020
Queue → IA
3y 3m
IA → COD
7y 9m
Total Duration
3y 3m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2027-12-15
Interconnection Agreement executed with PacifiCorp transmission
Proposed commercial operation date per queue filing
PacifiCorp-836 is a proposed 400 MW wind generation project located in Carbon County, Wyoming. The development project, sponsored by PacifiCorp, consists of 400 MW of wind capacity. It is actively listed in the PacifiCorp interconnection queue, with an original queue entry date of December 5, 2016. The proposed commercial operation date is October 1, 2023, and the Interconnection Agreement (IA) has been executed.
The point of interconnection for the project is the Aeolus substation. The project has appeared in recent news coverage regarding PacifiCorp's generation development plans in the West region.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
WY
County
Carbon
Grid Region
Mountain West
Market
—
Developer
PacifiCorp
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
ERIS
Point of Interconnection
Aeolus substation
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project PacifiCorp-836Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.