PacifiCorp-823
178 MW generation in Emery, UT · In queue since November 2016 · Proposed COD February 2027
178 MW
Capacity
1
Components
Solar
9y 8m
In Queue
IA Executed
IA Phase
Signed Jan 2020
Queue → IA
3y 2m
IA → COD
7y 1m
Total Duration
3y 2m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-02-01
Interconnection Agreement executed with PacifiCorp
Proposed commercial operation date per queue filing
PacifiCorp-823 is a proposed solar generation project with a total capacity of 178 MW, located in Emery County, Utah. The project is being developed by PacifiCorp Energy Supply Management and is interconnected with PacifiCorp. It is listed in the PacifiCorp interconnection queue as of November 15, 2016, with a proposed commercial operation date of June 30, 2019. The project's interconnection agreement has been executed.
The proposed project has been the subject of recent news coverage, with seven articles categorized as industry-related and concerning development.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
UT
County
Emery
Grid Region
Mountain West
Market
—
Developer
PacifiCorp Energy Supply Management
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
ERIS
Point of Interconnection
Emery substation
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-14
View all articlesNo Ask reports yet for this entity.
Ask about Project PacifiCorp-823Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.