PacifiCorp-805
95 MW generation in Kane, UT · In queue since September 2016 · Proposed COD December 2019
95 MW
Capacity
1
Components
Solar
9y 10m
In Queue
Suspended
IA Phase
Signed Apr 2020
Queue → IA
3y 7m
Total Duration
3y 7m
Schedule
80 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2019-12-19
PacifiCorp-805 is a proposed 95 MW solar generation project located in Kane County, Utah. The project, under development by Glen Canyon Solar A, LLC, is interconnected to PacifiCorp via the Sigurd-Glen Canyon transmission line.
The project entered the PacifiCorp interconnection queue on September 30, 2016, with a proposed commercial operation date of December 19, 2019. Its interconnection agreement status is currently listed as Suspended.
Generated from interconnection queue and public data sources
Realization risk through commissioning — schedule slippage, construction cost overrun, and COD probability vs the stated window. The diligence view that determines whether the project comes online when promised. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
UT
County
Kane
Grid Region
Mountain West
Market
—
Developer
Glen Canyon Solar A, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
ERIS
Point of Interconnection
Sigurd-Glen Canyon transmission line
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with curtailment risk decomposed by congestion zone and ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, first-year DSCR, and construction cost overrun exposure — what determines whether the deal clears its covenants once online. Projected across price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project PacifiCorp-805Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.