PacifiCorp-787
400 MW hybrid in Emery, UT · In queue since August 2016 · Proposed COD November 2024
400 MW
Capacity
1
Components
Solar
10y 3m
In Queue
IA Executed
IA Phase
Signed May 2019
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2y 9m
IA → COD
5y 6m
Total Duration
2y 9m
Schedule
25 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2024-11-15
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
rPlus Energies broke ground on the 400 MW solar PV + 400 MW/1,600 MWh battery Green River Energy Center.
businesswire.comResearch sources and reasoning (2 recorded sources)
medium confidence at research time
- businesswire.com/news/home/20240920988821/en/rPlus-Energies-Breaks-Ground-on-a-400-Megawatt-Solar-PV-and-400-MW1600-Megawatt-Hour-Battery-Green-River-Energy-Center
- businesswire.com/news/home/20241112886268/en/rPlus-Energies-Partners-with-Idaho-Power-and-Meta-on-Long-Term-Power-Purchase-Agreement-for-the-125-Megawatt-Pleasant-Valley-Solar-2-Project
Commercial operation date: No source gives a post-LBNL COD; the only date is the LBNL proposed COD of 2024-11-15. The Business Wire release shows groundbreaking on 2024-09-20 for the 400 MW solar + 1,600 MWh battery project, so that date is almost certainly stale. There is no explicit replacement date to adopt.
Developer: The LBNL filing entity 'Green River Solar I, LLC' is a project LLC. Business Wire coverage of the 400 MW Green River Energy Center groundbreaking names rPlus Energies as the developer, and a second release (Idaho Power/Meta PPA) also names rPlus.
Status: The Business Wire groundbreaking release dated 2024-09-20 shows the project moved from the queue into construction. LBNL still lists it as 'active', which is accurate for queue state but understates progress.
About
Generated Apr 10, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
PacifiCorp-787 is a proposed 400 MW hybrid solar and battery project located in Emery County, Utah. The development project, sponsored by Green River Solar I, LLC, consists of 400 MW of solar capacity. It is listed in the PacifiCorp interconnection queue as of August 8, 2016, with a proposed commercial operation date of November 15, 2018. The project's interconnection agreement (IA) has been executed.
The proposed project is listed in the West region and has appeared in recent news coverage related to industry and deals. Its point of interconnection (POI) is the Emery-Sigurd #2 line.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
UT
County
Emery
Grid Region
Mountain West
Market
—
Developer
Green River Solar I, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
ERIS
Point of Interconnection
Emery-Sigurd #2 line
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26