PacifiCorp-715
120 MW generation in Uinta, WY · In queue since October 2015 · Proposed COD January 2025
120 MW
Capacity
1
Components
Wind
11y 1m
In Queue
IA Executed
IA Phase
Signed Sep 2018
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
2y 11m
IA → COD
6y 4m
Total Duration
2y 11m
Schedule
22 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2025-01-30
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
Interconnection Agreement executed with PacifiCorp
lbnl_queueBLM issued decision approving road access project for wind facility
blm.govResearch sources and reasoning (1 recorded sources)
low confidence at research time
Commercial operation date: LBNL queue shows proposed COD of 2025-01-30. No independent news sources provide an updated target date, and the BLM road access approval (2025-01-13) suggests permitting is still in progress, making the January 2025 COD unlikely but uncontradicted by available evidence.
Developer: Both LBNL queue and BLM approval documents consistently identify 'Uinta Wind Energy LLC' as the developer. No parent company or operating entity is mentioned in available sources, suggesting this is the actual operating entity rather than a shell LLC.
Status: LBNL shows 'Active' status with IA executed in 2018. BLM road access decision issued January 13, 2025 indicates permitting milestones are still being completed, consistent with pre-construction active status.
About
Generated Apr 10, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
PacifiCorp-715 is a proposed wind generation project with a total capacity of 120 MW. The project is located in Uinta County, Wyoming, and is being developed by Uinta Wind Energy, LLC. It is interconnected to the PacifiCorp system at the Canyon Compression-Railroad transmission line point of interconnection.
The project entered the PacifiCorp interconnection queue on October 29, 2015, with a proposed commercial operation date of July 1, 2017. The interconnection agreement (IA) for the project has been executed. The project has been mentioned in recent news coverage related to regulatory matters.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
WY
County
Uinta
Grid Region
Mountain West
Market
—
Developer
Uinta Wind Energy, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
ERIS
Point of Interconnection
Canyon Compression-Railroad transmission line
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesNo Ask reports yet for this entity.
Ask about Project PacifiCorp-715Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.