PacifiCorp-642
58 MW hybrid in Iron, UT · In queue since February 2015 · Proposed COD December 2024
58 MW
Capacity
1
Components
Solar
11y 5m
In Queue
Suspended
IA Phase
Signed Sep 2016
Queue → IA
1y 7m
IA → COD
8y 3m
Total Duration
1y 7m
Schedule
19 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–30 months
Proposed COD: 2024-12-31
PacifiCorp-642 is a proposed 58 MW hybrid solar and battery project located in Iron County, Utah. The project, developed by Parowan Solar, LLC, consists of 58 MW of solar capacity. It is interconnected to the PacifiCorp grid at the Parowan substation.
The project is listed in the PacifiCorp interconnection queue with an entry date of February 9, 2015. The proposed commercial operation date was October 1, 2016. The interconnection agreement status is currently listed as Suspended, with an agreement date of September 8, 2016.
Generated from interconnection queue and public data sources
Realization risk through commissioning — schedule slippage, construction cost overrun, and COD probability vs the stated window. The diligence view that determines whether the project comes online when promised. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
UT
County
Iron
Grid Region
Mountain West
Market
—
Developer
Parowan Solar, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
ERIS
Point of Interconnection
Parowan substation
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with curtailment risk decomposed by congestion zone and ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, first-year DSCR, and construction cost overrun exposure — what determines whether the deal clears its covenants once online. Projected across price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project PacifiCorp-642Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.