PacifiCorp-634
99 MW generation in Beaver, UT · In queue since November 2014 · Proposed COD December 2025
99 MW
Capacity
1
Components
Solar
11y 8m
In Queue
IA Executed
IA Phase
Signed Sep 2016
Queue → IA
1y 10m
IA → COD
9y 3m
Total Duration
1y 10m
Schedule
7 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2025-12-15
PacifiCorp-634 is a proposed 99 MW solar generation project located in Beaver County, Utah. The project, developed by Fremont Solar, LLC, is interconnected to PacifiCorp via the Parowan-Sigurd line. It entered the PacifiCorp interconnection queue on November 20, 2014, and has an Interconnection Agreement (IA) executed on September 9, 2016. The proposed commercial operation date (COD) is December 31, 2016.
The project consists of 99 MW of solar photovoltaic generation capacity. Its interconnection status is listed as active.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
UT
County
Beaver
Grid Region
Mountain West
Market
—
Developer
Fremont Solar, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
ERIS
Point of Interconnection
Parowan-Sigurd line
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- FOURCORNERS
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project PacifiCorp-634Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.