PacifiCorp-443
34.56 MW generation in Crook, OR · In queue since October 2012 · Proposed COD December 2020
34.56 MW
Capacity
1
Components
Solar
13y 9m
In Queue
IA Executed
IA Phase
Signed Jun 2020
Queue → IA
7y 8m
IA → COD
6 months
Total Duration
7y 8m
Schedule
68 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2020-12-01
PacifiCorp-443 is a proposed 34.56 MW hybrid solar and battery project located in Crook County, Oregon. The project, developed by Ponderosa Solar, LLC, consists of 34.56 MW of solar capacity. It is interconnected to the PacifiCorp grid at the Ponderosa substation.
The project is listed in the PacifiCorp interconnection queue with an entry date of October 16, 2012, and a proposed commercial operation date of June 30, 2015. The interconnection agreement for the project has been executed as of June 5, 2020.
Generated from interconnection queue and public data sources
Realization risk from now to commercial operation — financing close, EPC and tax-equity counterparty mix, and COD probability vs the proposed date. The diligence view that determines whether the deal actually closes. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
OR
County
Crook
Grid Region
Mountain West
Market
—
Developer
Ponderosa Solar, LLC
Utility
PacifiCorp
Entity
PacifiCorp
Service Type
ERIS
Point of Interconnection
Ponderosa substation
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile will look like once it commissions. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — first-year production estimate and 10-year P50 trajectory, with probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. First-year DSCR, 10-year cashflow, and counterparty exposure across price and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- MOUNTAIN_WEST
- Trading Hub
- MID-C
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Project PacifiCorp-443Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.