Malta Project
225 MW storage in Brevard, FL · In queue since March 2023 · Proposed COD December 2026
225 MW
Capacity
1
Components
Battery
3y 8m
In Queue
Facility Study
IA Phase
COD target: 2026
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
3y 9m
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-30
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Milestones in this assessment
Entered OUC interconnection queue, Facility Study phase
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available with proposed COD of 2026-12-30. No independent news or research sources found to validate or contradict this date.
Developer: LBNL snapshot lists developer as null. No press releases, corporate announcements, or news coverage found identifying the project developer or operating entity.
Status: LBNL reports 'active' status in Facility Study phase. No contradicting information or advancement signals found in public sources.
About
Generated Apr 10, 2026
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
The Malta Project is a proposed 225 MW battery storage project located in Brevard County, Florida. The project is being developed by Orlando Utilities Commission (OUC) and has appeared in recent news coverage. It is interconnected to the OUC Indian River Plant.
The project is listed in the Orlando Utilities Commission interconnection queue as OUC-202311, with an entry date of March 6, 2023. The proposed commercial operation date is December 30, 2026. The project's interconnection status is currently in the Facility Study phase.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- LBNL queue source as of: Dec 31, 2025.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
FL
County
Brevard
Grid Region
Southeast
Market
—
Developer
—
Utility
Orlando Utilities Commission
Entity
OUC
Service Type
NRIS
Point of Interconnection
OUC Indian River Plant
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- SOUTHEAST
- Trading Hub
- FRCC
- Hub Confidence
- UNKNOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-04-09