Bay Breeze solar
150 MW generation in Jefferson, NY · In queue since August 2026
150 MW
Capacity
0
Components
2 months
In Queue
—
IA Status
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
2 months
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
Bay Breeze Solar is a proposed 150 MW solar generation project in Jefferson County, New York. The project is being developed by Bay Breeze Solar, LLC and would connect to the electric grid at the North Watertown (Lyme Junction)–Lyme Line 13, a 115 kV transmission line. The transmission owner for the point of interconnection is listed as NM-NG.
The project is in the interconnection queue of the New York Independent System Operator (NYISO) under queue identifier NYISO-C26-0030, with a recorded queue entry date of August 25, 2026. Its status in the queue is active. The available data does not specify a proposed commercial operation date or the status of an interconnection agreement.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NY
County
Jefferson
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Bay Breeze Solar, LLC
Utility
Transmission Owner NM-NG Transmission Owner NaN Name: 228, dtype: object
Entity
NYISO
Service Type
—
Point of Interconnection
North Watertown (Lyme Junction)-Lyme Line 13 115 kV
Data Source
Live · NYISO
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- NYISO
- Trading Hub
- ZONE D
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- NORTH
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Bay Breeze solarForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.