Town Line Solar CSR Phase I
240 MW hybrid in Sullivan, NY · In queue since October 2024 · Proposed COD May 2030
240 MW
Capacity
1
Components
Solar
1y 9m
In Queue
—
IA Status
COD target: 2030
Total Duration
5y 7m
Study Phase
C24
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-05-01
NYISO interconnection queue application submitted
The Town Line Solar CSR Phase I project is a proposed 240 MW solar and battery hybrid project located in Sullivan County, New York. Developed by RWE Solar Development, LLC, the project consists of 240 MW of solar generation. It is interconnected to the NYISO queue under queue ID NYISO-C24-363, with an entry date of October 15, 2024, and a proposed commercial operation date of December 1, 2027.
The project is slated to connect to the Coopers Corner to Middletown Tap 345 kV Line. The designated utility is NYPA, and the project is currently listed as active within the NYISO interconnection queue. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NY
County
Sullivan
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
RWE Solar Development, LLC
Utility
NYPA
Entity
NYISO
Service Type
—
Point of Interconnection
Coopers Corner to Middletown Tap 345 kV Line
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- NYISO
- Trading Hub
- ZONE G
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- SHOEMAKER___GT
- POI Substation
- Middletown Tap
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Town Line Solar CSR Phase IForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.