Amsterdam Solar
150 MW generation in Montgomery, NY · In queue since October 2024 · Proposed COD July 2028
150 MW
Capacity
1
Components
Solar
1y 9m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 9m
Study Phase
C24
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-07-01
Entered NYISO interconnection queue as C24-362
The Amsterdam Solar project is a proposed 150 MW solar generation facility in Montgomery County, New York. Developed by RWE Solar Development, LLC, the project entered the NYISO interconnection queue as queue ID NYISO-C24-362 on October 15, 2024. The proposed commercial operation date is December 1, 2027.
The project is currently listed as active in the NYISO queue. The point of interconnection is the Edic - Gordon Road 345 kV, Line 14. Recent news coverage has discussed the development.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NY
County
Montgomery
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
RWE Solar Development, LLC
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
Edic - Gordon Road 345 kV, Line 14
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- NYISO
- Trading Hub
- ZONE E
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Amsterdam SolarForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.