Hickling Storage, LLC
90 MW storage in Steuben, NY · In queue since October 2024 · Proposed COD December 2027
90 MW
Capacity
1
Components
Battery
1y 7m
In Queue
—
IA Status
COD target: 2027
Total Duration
3y 2m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-01
Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Hickling Storage, LLC is proposing a 90 MW battery storage project in Steuben County, New York. The project, developed by Hickling Storage, LLC, is currently active in the New York Independent System Operator (NYISO) interconnection queue under queue ID NYISO-C24-350. The project entered the queue on October 14, 2024, and has a proposed commercial operation date of December 1, 2027. The point of interconnection is the 115kV Hickling Substation, and the serving utility is NYSEG.
The proposed project consists solely of battery storage, with a total capacity of 90 MW. As of the current data, there is no indication of an executed Interconnection Agreement (IA) for the project, nor is there a match to an existing operating plant in the Energy Information Administration (EIA) database. Recent news coverage of the project is also not indicated in the available data.
Generated from interconnection queue and public data sources
State
NY
County
Steuben
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Hickling Storage, LLC
Utility
NYSEG
Entity
NYISO
Service Type
—
Point of Interconnection
115kV Hickling Substation
Data Source
LBNL
Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- NYISO
- Trading Hub
- ZONE B
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- HICKLING___1
- POI Substation
- Hickling
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Hickling Storage, LLCForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.