Stoner Trail Storage
100 MW storage in Fulton, NY · In queue since October 2024 · Proposed COD August 2028
100 MW
Capacity
1
Components
Battery
1y 7m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 10m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-08-01
Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
The Stoner Trail Storage project is a proposed 100 MW battery storage project located in Fulton County, New York. Developed by Granada Solar, LLC, the project is interconnected within the New York Independent System Operator (NYISO) queue as entry NYISO-C24-332, with a queue entry date of October 9, 2024. The proposed commercial operation date is August 1, 2028.
The project consists of 100 MW of battery storage capacity. Interconnection will be made at the Inghams-Stoner 115kV line 9 and Meco-Maple Ave 115kV line 22. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
NY
County
Fulton
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Granada Solar, LLC
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
Inghams-Stoner 115kV line 9 and Meco-Maple Ave 115kV line 22
Data Source
LBNL
Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- NYISO
- Trading Hub
- ZONE E
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Stoner Trail StorageForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.