Lockport Storage
180 MW storage in Niagara, NY · In queue since October 2024 · Proposed COD December 2028
180 MW
Capacity
1
Components
Battery
1y 9m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 2m
Study Phase
C24
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-01
NYISO interconnection queue application submitted
Lockport Storage is a proposed 180 MW battery storage project located in Niagara County, New York. Developed by Origis Development LLC, the project is interconnected to the NYSEG utility via the Robinson Road 230 kV point of interconnection. The project entered the NYISO interconnection queue (queue ID NYISO-C24-326) on October 8, 2024, and has a proposed commercial operation date of December 1, 2028.
The Lockport Storage project consists of 180 MW of battery storage capacity. The project is currently listed as active in the NYISO interconnection queue. The development has appeared in recent news coverage regarding energy storage projects in New York.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NY
County
Niagara
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Origis Development LLC
Utility
NYSEG
Entity
NYISO
Service Type
—
Point of Interconnection
Robinson Road 230 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- NYISO
- Trading Hub
- ZONE A
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Lockport StorageForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.