NY Chateaugay 0 Willis Rd Storage
150 MW storage in Franklin, NY · In queue since October 2024 · Proposed COD April 2028
150 MW
Capacity
1
Components
Battery
1y 9m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 6m
Study Phase
C24
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-04-01
Northern New York Energy Storage Project achieved commercial operation
sourceThe NY Chateaugay 0 Willis Rd Storage project is a proposed 150 MW battery storage project located in Franklin County, New York. The developer is Chateauguay River, LLC, and the interconnecting utility is the New York Power Authority (NYPA). The project is in the New York Independent System Operator (NYISO) interconnection queue as entry NYISO-C24-304-004, with a queue entry date of October 1, 2024, and a proposed commercial operation date of April 1, 2028.
The project is planned to interconnect at the Willis 230kV substation. The project has appeared in recent news coverage related to grid development.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NY
County
Franklin
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Chateauguay River, LLC
Utility
NYPA
Entity
NYISO
Service Type
—
Point of Interconnection
Willis 230kV substation
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- NYISO
- Trading Hub
- ZONE D
- Hub Confidence
- HIGH
- POI Substation
- Willis Road Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesNo Ask reports yet for this entity.