Cazenovia Solar
80 MW generation in Madison, NY · In queue since September 2024 · Proposed COD October 2029
80 MW
Capacity
1
Components
Solar
1y 8m
In Queue
—
IA Status
COD target: 2029
Total Duration
5y 1m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-10-01
Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Cazenovia Solar is a proposed 80 MW solar generation project located in Madison County, New York. The project, developed by ACE DevCo NC, LLC, is in the New York Independent System Operator (NYISO) interconnection queue as entry NYISO-C24-290, with a queue entry date of September 27, 2024. The proposed commercial operation date is October 1, 2029.
The Cazenovia Solar project is currently listed as active in the interconnection queue. It is proposed to interconnect to the Fenner-Shippey Line 3 115 kV. The project has been the subject of recent news coverage, with four articles categorized as regulatory and industry news.
Generated from interconnection queue and public data sources
State
NY
County
Madison
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
ACE DevCo NC,LLC
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
Fenner-Shippey Line 3 115 kV
Data Source
LBNL
Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- NYISO
- Trading Hub
- ZONE C
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Cazenovia SolarForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.