Bassett Energy Storage
79.9 MW storage in Steuben, NY · In queue since September 2024 · Proposed COD July 2028
79.9 MW
Capacity
1
Components
Battery
1y 10m
In Queue
—
IA Status
COD target: 2028
Total Duration
3y 10m
Study Phase
C24
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-07-01
Bassett Energy Storage is a proposed 79.9 MW battery storage project located in Steuben County, New York. The project, developed by Bassett Energy Storage, is interconnected to the New York Independent System Operator (NYISO) queue under queue ID NYISO-C24-270. The project entered the queue on September 24, 2024, with a proposed commercial operation date of July 1, 2027. The point of interconnection is the Spencer Hill 115 kV Substation, served by utility NYSEG.
The Bassett Energy Storage project has been featured in recent news coverage.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NY
County
Steuben
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Bassett Energy Storage
Utility
NYSEG
Entity
NYISO
Service Type
—
Point of Interconnection
Spencer Hill 115 kV Substation
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- NYISO
- Trading Hub
- ZONE B
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Bassett Energy StorageForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.