Shallow Seam BESS (NYISO-C24-233) — Project Summary

Queue ID
NYISO-C24-233
Capacity
400 MW
Technology
Battery
Status
active
Location
Clearfield, PA
Region
NYISO
Developer
Shallow Seam Energy Storage, LLC
IA Status
—

Shallow Seam BESS

NYISO-C24-233BetaActiveBatteryNYISOLBNL + Live

400 MW storage in Clearfield, PA · In queue since September 2024 · Proposed COD March 2029

BA: PJMISO/RTO: NYISONERC: RFCRC: PJM

400 MW

Capacity

1

Components

Battery

2y 2m

In Queue

—

IA Status

COD target: 2029

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

4y 6m

Study Phase

C24

Pre-Study0%
Queue EntrySep 22, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-03-01

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
Mar 1, 2029
From queue filing
Developer in saved assessment
Shallow Seam Energy Storage, LLC
From queue filing
Status at research time
Active
Active in the queue (LBNL data through 2025-12-31). One aggregator page (interxdata, queue ID 1632, dated 2026-10-12) lists a 'Shallow Seam BESS' of the same size and POI as withdrawn. This is unverified and may be a duplicate or re-keyed record.
Financing
Not recorded
Research sources and reasoning (5 recorded sources)

low confidence at research time

  1. app.nrgmap.com/queues/lbnl-nyiso-c24-233
  2. interconnection.fyi/project/nyiso-c24-233
  3. cleanview.co/power-projects/planned/battery-storage-projects/pennsylvania/C24-233_shallow_seam_bess/shallow-seam-bess
  4. interxdata.com/projects/shallow-seam-bess-nyiso-queue-1632/
  5. bizapedia.com/pa/shallow-seam-energy-storage-llc.html

Commercial operation date: Only the LBNL proposed COD of 2029-03-01 exists. The aggregator pages (Cleanview 'Expected online 2029', interconnection.fyi 'February 28, 2029', NRG Map) all repeat the LBNL data, so they are not independent confirmation. No developer press release or news gives a financing-backed target.

Developer: Every source names only the project LLC, which has a Pennsylvania registration (Bizapedia, Boston, PA). No parent or operating company, press release, or acquisition could be found, so the LLC name is kept as-is.

Status: LBNL and the other aggregators show the queue position as active, and no primary source such as NYISO or PJM confirms a withdrawal. The conflicting interxdata record, which carries a different queue ID, is flagged but not adopted.

About

Saved background

Generated Apr 10, 2026 · Predates Sep 30, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Shallow Seam BESS project is a proposed 400 MW battery storage project located in Clearfield County, Pennsylvania. Developed by Shallow Seam Energy Storage, LLC, the project is interconnected within the New York Independent System Operator (NYISO) queue as entry NYISO-C24-233. The proposed commercial operation date is December 1, 2026, with a queue entry date of September 22, 2024.

The project is slated to connect to the Homer City - Mainesburg 345kV Line (L47) and is currently listed as active in the interconnection queue.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • NYISO queue source as of: Sep 30, 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

PA

County

Clearfield

Grid Region

NYISO (New York)

Market

ISO/RTO Member

Developer

Shallow Seam Energy Storage, LLC

Utility

NYSEG

Entity

NYISO

Service Type

—

Point of Interconnection

Homer City - Mainesburg 345kV Line (L47)

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
NYISO
Trading Hub
ZONE F
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.