North Country Wind
380 MW generation in Franklin, NY · In queue since September 2024 · Proposed COD June 2029
380 MW
Capacity
1
Components
Wind
1y 8m
In Queue
—
IA Status
COD target: 2029
Total Duration
4y 9m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-06-01
Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
The North Country Wind project is a proposed 380 MW wind generation facility located in Franklin County, New York. Developed by NY North Country, LLC, the project was entered into the NYISO interconnection queue (queue ID NYISO-C24-189) on September 18, 2024. The proposed commercial operation date is June 1, 2029. The point of interconnection is the Willis 230kV substation.
The project is currently listed as active in the NYISO queue. The designated utility for the project is NYPA. Recent news coverage has discussed the development project.
Generated from interconnection queue and public data sources
State
NY
County
Franklin
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
NY North Country, LLC
Utility
NYPA
Entity
NYISO
Service Type
—
Point of Interconnection
Willis 230kV substation
Data Source
LBNL + Live
Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- NYISO
- Trading Hub
- ZONE D
- Hub Confidence
- HIGH
- POI Substation
- Willis Road Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesNo Ask reports yet for this entity.
Ask about North Country WindForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.