Stargazer II
325 MW hybrid in Mckean, PA · In queue since September 2024 · Proposed COD July 2029
325 MW
Capacity
1
Components
Solar
2y 2m
In Queue
—
IA Status
COD target: 2029
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
4y 10m
Study Phase
C24
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-07-01
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
Research sources and reasoning (5 recorded sources)
low confidence at research time
- interconnection.fyi/project/nyiso-c24-176
- protectmckeancountywilds.com/rwe-stargazer.html
- nyiso.com/documents/20142/50558845/02_03%2024%202025%20-%20Interconnection%20Cluster%20Study_%20Projects%20Dashboard%202025%20R11.pdf/e4e8b0d6-f5ce-4cd8-a640-761210eb5dc6
- nyiso.com/documents/20142/57604192/05%2002%202026%20-%20Interconnection%20Cluster%20Study_%20Projects%20Dashboard%202026%20R0.pdf/37e74a5f-2753-8dc7-1a1a-e1b826637f30
- facebook.com/groups/1252882242965493/posts/1407993150787734/
Commercial operation date: Only the queue-derived date exists. Community posts cite 'a proposed completion date of July 1, 2029', but they are repeating the NYISO filing, not giving an independent developer target. No press release or financing-backed COD was found.
Developer: The NYISO cluster dashboards list RWE Solar Development, LLC as the filing entity. Local coverage and the project pages consistently describe the developer as RWE, which markets the combined 'Stargazer Solar' project. No ownership transfer was found.
Status: The March 2025 and 2026 NYISO cluster dashboards both list C24-176 as active, matching the LBNL status. No source shows withdrawal, an executed IA, or construction.
About
Generated Apr 10, 2026 · Predates Sep 30, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Stargazer II is a proposed 325 MW hybrid solar and battery project located in McKean County, Pennsylvania. The project, developed by RWE Solar Development, LLC, consists of 325 MW of solar capacity. It is currently active in the New York Independent System Operator (NYISO) interconnection queue as entry NYISO-C24-176, with a queue entry date of September 17, 2024. The proposed commercial operation date is December 1, 2027.
The project intends to interconnect to the NYSEG utility grid at the Homer City to Pierce Brook 345 kV Line.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- NYISO queue source as of: Sep 30, 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
PA
County
Mckean
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
RWE Solar Development, LLC
Utility
NYSEG
Entity
NYISO
Service Type
—
Point of Interconnection
Homer City to Pierce Brook 345 kV Line
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- NYISO
- Trading Hub
- ZONE F
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.