KCE NY 34
100 MW storage in Ulster, NY · In queue since September 2024 · Proposed COD December 2028
100 MW
Capacity
1
Components
Battery
1y 8m
In Queue
—
IA Status
COD target: 2028
Total Duration
4y 3m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-01
Forward-looking exposure analytics for this queue project — climate hazards, expected generation variability, counterparty risk — into a single decision-grade view. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
KCE NY 34 is a proposed 100 MW battery storage project located in Ulster County, New York. The project, developed by KCE NY 34, LLC, is interconnected to Central Hudson Gas & Electric (CHGE) via the Saugerties 69 kV point of interconnection. It is listed in the New York Independent System Operator (NYISO) interconnection queue as project number NYISO-C24-173, with an entry date of September 17, 2024.
The proposed commercial operation date for KCE NY 34 is December 1, 2028. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
NY
County
Ulster
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
KCE NY 34, LLC
Utility
CHGE
Entity
NYISO
Service Type
—
Point of Interconnection
Saugerties 69 kV
Data Source
LBNL + Live
Forward-looking generation outlook for this queue project with probabilistic ranges across weather, demand, and policy scenarios. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR bands, and refinancing risk for this queue project, projected under price, demand, and policy scenarios. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- NYISO
- Trading Hub
- ZONE G
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about KCE NY 34Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.