Basecamp BESS (NYISO-C24-097) — Project Summary

Queue ID
NYISO-C24-097
Capacity
170 MW
Technology
Battery
Status
active
Location
Chautauqua, NY
Region
NYISO
Developer
RWE Solar Development, LLC
IA Status
—

Basecamp BESS

NYISO-C24-097BetaActiveBatteryNYISOLBNL + Live

170 MW storage in Chautauqua, NY · In queue since August 2024 · Proposed COD February 2029

BA: NYISISO/RTO: NYISONERC: NPCCRC: NYIS

170 MW

Capacity

1

Components

Battery

2y 3m

In Queue

—

IA Status

COD target: 2029

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

4y 6m

Study Phase

C24

Pre-Study0%
Queue EntryAug 26, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-02-01

News-reported activity
as of 21 months ago

From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.

Latest milestoneCOD achievedSolar Builder · 2023-03-30
Expected COD2028observertoday.com · 2025-02-04

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Sep 30, 2026 queue source. See the queue record for reported project facts.

Research COD
Feb 1, 2029
From queue filing
Developer in saved assessment
RWE Clean Energy
Filed as RWE Solar Development, LLC
Status at research time
Active
Active — early-stage queue entry filed August 2024, no construction or permitting announcements yet
Financing
Not recorded

Milestones in this assessment

IA executedAug 26, 2024Latest in this assessment

Entered NYISO interconnection queue as C24-097

Research sources and reasoning (0 recorded sources)

low confidence at research time

No source list recorded with this assessment.

Commercial operation date: Only LBNL queue data available with proposed COD of February 2029. No independent news or press releases found to validate or contradict this target date.

Developer: LBNL filing entity 'RWE Solar Development, LLC' is a project development subsidiary. Parent operating company is RWE Clean Energy (formerly RWE Renewables Americas), the U.S. renewable energy arm of German utility RWE AG.

Status: LBNL status shows active queue position. Project entered interconnection queue in August 2024, making it very early-stage with 5-year horizon to proposed COD. No public announcements found regarding permits, financing, or development milestones.

About

Saved background

Generated Apr 10, 2026 · Predates Sep 30, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Basecamp BESS is a proposed 170 MW battery storage project located in Chautauqua County, New York. The project, developed by RWE Solar Development, LLC, is interconnected within the New York Independent System Operator (NYISO) queue under queue ID NYISO-C24-097. The project entered the queue on August 26, 2024, with a proposed commercial operation date of December 1, 2027.

The project consists of 170 MW of battery storage capacity. It is listed as active in the interconnection queue and has been the subject of recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • NYISO queue source as of: Sep 30, 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

NY

County

Chautauqua

Grid Region

NYISO (New York)

Market

ISO/RTO Member

Developer

RWE Solar Development, LLC

Utility

NM-NG

Entity

NYISO

Service Type

—

Point of Interconnection

Laona Station 115kV

Data Source

LBNL + Live

DeveloperNorthland Power, Inc.±observertoday.com · 2025-02-04
CompanyDuke EnergyReuters · 2024-02-09
AgencyDOEReuters · 2023-12-06
RulingOrderReuters · 2023-12-06
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
NYISO
Trading Hub
ZONE A
Hub Confidence
HIGH
POI Substation
Avon Station

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

Insights & Articles (4)Beta

Last updated 2026-03-26

View all articles
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.