Highbush Energy Storage (NYISO-C24-062) — Project Summary

Queue ID
NYISO-C24-062
Capacity
200 MW
Technology
Battery
Status
active
Location
Dutchess, NY
Region
NYISO
Developer
Hanwha Q CELLS USA Corp.
IA Status
—

Highbush Energy Storage

NYISO-C24-062BetaActiveBatteryNYISOLBNL + Live

200 MW storage in Dutchess, NY · In queue since August 2024 · Proposed COD December 2027

BA: NYISISO/RTO: NYISONERC: NPCCRC: NYIS

200 MW

Capacity

1

Components

Battery

2y 3m

In Queue

—

IA Status

COD target: 2027

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Total Duration

3y 4m

Study Phase

C24

Pre-Study0%
Queue EntryAug 1, 2024

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-01

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Sep 30, 2026 queue source. See the queue record for reported project facts.

Research COD
Dec 1, 2027
From queue filing
Developer in saved assessment
Hanwha Q CELLS USA Corp.
From queue filing
Status at research time
Active
Active — queue position secured August 2024, no public construction timeline announced
Financing
Not recorded

Milestones in this assessment

IA executedAug 2024Latest in this assessment

Entered NYISO interconnection queue as C24-062

Research sources and reasoning (0 recorded sources)

low confidence at research time

No source list recorded with this assessment.

Commercial operation date: Only LBNL queue data available with proposed COD of December 2027. No independent news or press releases found to validate or contradict this target date.

Developer: LBNL lists Hanwha Q CELLS USA Corp. as developer. No evidence of shell LLC structure or ownership changes found in available sources.

Status: LBNL status shows active queue position entered August 2024. No news coverage found regarding permitting, financing, or construction milestones.

About

Saved background

Generated Apr 10, 2026 · Predates Sep 30, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Highbush Energy Storage project is a proposed 200 MW battery storage project located in Dutchess County, New York. Developed by Hanwha Q CELLS USA Corp., the project is currently active in the New York Independent System Operator (NYISO) interconnection queue as entry NYISO-C24-062, with a queue entry date of August 1, 2024. The proposed commercial operation date is December 1, 2027, and the point of interconnection is the Manchester 115kV substation.

The project consists of 200 MW of battery storage capacity. The proposed project is in the Central Hudson Gas & Electric (CHGE) service area. The Highbush Energy Storage project has appeared in recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • NYISO queue source as of: Sep 30, 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

NY

County

Dutchess

Grid Region

NYISO (New York)

Market

ISO/RTO Member

Developer

Hanwha Q CELLS USA Corp.

Utility

CHGE

Entity

NYISO

Service Type

—

Point of Interconnection

Manchester 115 kV

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
NYISO
Trading Hub
ZONE G
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No insights available for this project.
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.