Oakdale Battery Storage LLC
150 MW storage in Broome, NY · In queue since August 2024 · Proposed COD August 2030
150 MW
Capacity
1
Components
Battery
1y 11m
In Queue
—
IA Status
COD target: 2030
Total Duration
6 years
Study Phase
C24
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-08-01
Entered NYISO interconnection queue as C24-032
The Oakdale Battery Storage LLC project is a proposed 150 MW battery storage development in Broome County, New York. The project, being developed by BayWa r.e. Solar Projects LLC, is interconnected to the New York Independent System Operator (NYISO) queue under queue ID NYISO-C24-032. The project entered the queue on August 1, 2024, with a proposed commercial operation date of May 1, 2028.
The project consists of 150 MW of battery storage capacity. The point of interconnection is the Oakdale 115 kV substation, and the interconnecting utility is NYSEG. The project is currently listed as active in the NYISO interconnection queue.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NY
County
Broome
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
BayWa r.e Projects LLC.
Utility
NYSEG
Entity
NYISO
Service Type
—
Point of Interconnection
Oakdale 115 kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- NYISO
- Trading Hub
- ZONE C
- Hub Confidence
- HIGH
- POI Substation
- Oakdale Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Oakdale Battery Storage LLCForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.