Blue Spruce Storage
300 MW storage in Bronx, NY · In queue since August 2024 · Proposed COD August 2028
300 MW
Capacity
1
Components
Battery
1y 11m
In Queue
—
IA Status
COD target: 2028
Total Duration
4 years
Study Phase
C24
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-08-01
Entered NYISO interconnection queue as C24-005
Blue Spruce Storage is a proposed 300 MW battery storage project located in Bronx County, New York. The project, developed by Blue Spruce Storage LLC, is interconnected to the ConEd utility via the Mott Haven 138KV Bus. It entered the NYISO interconnection queue as project NYISO-C24-005 on August 1, 2024, and has a proposed commercial operation date of August 1, 2028.
The project is currently listed as active in the NYISO queue. Recent news coverage has discussed the development.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NY
County
Bronx
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Blue Spruce Storage LLC
Utility
ConEd
Entity
NYISO
Service Type
—
Point of Interconnection
Mott Haven 138KV Bus
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- NYISO
- Trading Hub
- ZONE J
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- MOTTHAVN_138_KV_9M4_REV_LBMP_J
- POI Substation
- Mott Haven Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Blue Spruce StorageForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.