Garnet Energy Center (NYISO-883) — Project Summary

Queue ID
NYISO-883
Capacity
200 MW
Technology
Solar
Status
active
Location
Cayuga, NY
Region
NYISO
Developer
Garnet Energy Center, LLC
IA Status
Facility Study

Garnet Energy Center

NYISO-883BetaActiveSolarNYISOLBNL + Live

200 MW generation in Cayuga, NY · In queue since June 2019 · Proposed COD April 2028

BA: NYISISO/RTO: NYISONERC: NPCCRC: NYIS

200 MW

Capacity

1

Components

Solar

7y 5m

In Queue

Facility Study

IA Phase

Signed Jan 2023

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

3y 7m

IA → COD

5y 3m

Total Duration

3y 7m

Construction50%
Queue EntryJun 11, 2019

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection AgreementJan 11, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Interconnection Queue; status 11

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2028-04-01

News-reported activity
as of 6y 9m ago

From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.

Latest activityConstruction startSyracuse.com · 2020-02-29

Cross-source intelligence

Saved research · Beta
Researched Jun 1, 2026

Experimental assessment saved at the research date. Predates the Sep 30, 2026 queue source. See the queue record for reported project facts.

Research COD
Apr 1, 2028
From queue filing
Developer in saved assessment
Garnet Energy Center, LLC
From queue filing
Status at research time
Active
Active — Facility Study stage as of January 2023, no recent construction or permitting updates found
Financing
Not recorded

Milestones in this assessment

IA executedJan 11, 2023Latest in this assessment

Facility Study phase initiated in NYISO queue

lbnl_queue_snapshot
Research sources and reasoning (1 recorded sources)

low confidence at research time

  1. syracuse.com/news/2020/02/monster-cny-solar-farm-would-replace-corn-and-soybeans-with-power-for-30000-homes.html

Commercial operation date: Only LBNL queue data provides a COD target of April 2028. No recent news or press releases confirm or update this date. The 2020 Syracuse.com article predates the LBNL proposed COD and provides no specific timeline.

Developer: Only the LBNL filing entity 'Garnet Energy Center, LLC' is available. No news sources identify a parent company or operating entity behind this project-specific LLC. Unable to determine if this is a shell entity or the actual developer.

Status: LBNL shows 'active' status with Facility Study initiated January 2023. The 2020 news article mentioned construction start but predates the interconnection study phase, suggesting project timeline has shifted significantly.

About

Saved background

Generated Apr 10, 2026 · Predates Sep 30, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

The Garnet Energy Center is a proposed 200 MW solar generation project located in Cayuga County, New York. Developed by Garnet Energy Center, LLC, the project is interconnected to the NYISO grid at the Pannell - Clay 345kV point of interconnection. It entered the NYISO interconnection queue as queue ID NYISO-883 on June 11, 2019, and has a proposed commercial operation date of November 1, 2025. Its interconnection status is currently in the Facility Study phase.

The Garnet Energy Center development project has been the subject of recent news coverage.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • NYISO queue source as of: Sep 30, 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

NY

County

Cayuga

Grid Region

NYISO (New York)

Market

ISO/RTO Member

Developer

Garnet Energy Center, LLC

Utility

NYPA

Entity

NYISO

Service Type

—

Point of Interconnection

Pannell - Clay 345kV

Data Source

LBNL + Live

Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
NYISO
Trading Hub
ZONE C
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

Insights & Articles (1)Beta

Last updated 2026-03-26

View all articles
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.