Riverside Solar
100 MW generation in Jefferson, NY · In queue since June 2019 · Proposed COD December 2027
100 MW
Capacity
1
Components
Solar
7y 5m
In Queue
Facility Study
IA Phase
COD target: 2027
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
8y 6m
Interconnection request submitted to ISO/RTO
Interconnection Queue; status 10
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-01
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Sep 30, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Entered NYISO queue and began Facility Study phase
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available with proposed COD of December 2027. No independent news or press releases found to validate or update this target date.
Developer: Only LBNL filing entity 'Riverside Solar, LLC' is available. No news coverage found to identify parent company or operating entity behind this project-specific LLC.
Status: LBNL reports 'active' status with 'Facility Study' interconnection phase. No contradicting information or advancement signals found in available sources.
About
Generated Apr 10, 2026 · Predates Sep 30, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Riverside Solar is a proposed 100 MW solar generation project located in Jefferson County, New York. Developed by Riverside Solar, LLC, the project is interconnected to the NYISO grid at the Lyme Substation 115kV. It entered the NYISO interconnection queue as queue ID NYISO-882 on June 10, 2019.
The proposed commercial operation date (COD) for Riverside Solar is December 1, 2027. The project's interconnection status is currently in the System Impact Study phase. The project has appeared in recent news.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- NYISO queue source as of: Sep 30, 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NY
County
Jefferson
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Riverside Solar, LLC
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
Lyme Substation 115kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- NYISO
- Trading Hub
- ZONE D
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
KCE NY 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
KCE NY 31
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
KCE NY 21
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
KCE NY 30
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.