Luyster Creek Energy Storage 1
57.3 MW storage in Queens, NY · In queue since May 2019 · Proposed COD January 2027
57.3 MW
Capacity
1
Components
Battery
7y 2m
In Queue
System Impact Study
IA Phase
Signed Feb 2023
Queue → IA
3y 9m
IA → COD
3y 11m
Total Duration
3y 9m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 6–18 months
Proposed COD: 2027-01-01
Luyster Creek Energy Storage 1 is a proposed 57.3 MW battery storage project located in Queens County, New York. The project, being developed by Astoria Generating Company, LP, is interconnected to the ConEd utility via the Astoria West 138kV point of interconnection. It entered the NYISO interconnection queue as queue ID NYISO-835 on May 7, 2019, and has a proposed commercial operation date of May 1, 2026. The project's interconnection status is currently in the System Impact Study phase.
The Luyster Creek Energy Storage 1 project has been mentioned in recent news coverage.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NY
County
Queens
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Eastern Generation, LLC
Utility
ConEd
Entity
NYISO
Service Type
—
Point of Interconnection
Astoria West 138kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- NYISO
- Trading Hub
- ZONE J
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- NGRID_A4_DSASP
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all articlesNo Ask reports yet for this entity.
Ask about Luyster Creek Energy Storage 1Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.