Cider Solar
500 MW generation in Genesee, NY · In queue since April 2019 · Proposed COD January 2027
500 MW
Capacity
1
Components
Solar
7y 7m
In Queue
System Impact Study
IA Phase
Signed Jan 2023
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
3y 9m
IA → COD
4 years
Total Duration
3y 9m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Interconnection Queue; status 12
Project under construction
Typical: 12–24 months
Proposed COD: 2027-01-01
From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.
Cross-source intelligence
Experimental assessment saved at the research date. See the queue record for reported project facts.
- —·Hecate Energy (Hecate Energy Cider Solar LLC)→Greenbacker Renewable Energy Companygreenbackercapital.com
Milestones in this assessment
New York State (ORES) approved the permit for Hecate's Cider Solar, then the state's largest solar project.
pv-tech.orgGreenbacker announced the start of major construction activities on Cider Solar Farm.
greenbackercapital.comGreenbacker closed $440M in tax equity financing for the project.
pv-magazine-usa.comResearch sources and reasoning (7 recorded sources)
medium confidence at research time
- greenbackercapital.com/resources/construction-begins-on-new-yorks-largest-solar-energy-project
- pv-magazine-usa.com/2026/02/11/greenbacker-secures-440-million-tax-equity-for-new-yorks-largest-solar-project/
- mercomcapital.com/greenbacker-closes-440m-tax-equity-financing-cider-solar-project/
- finance.yahoo.com/news/energy-transition-cider-solar-project-113813472.html
- pv-tech.org/hecate-energy-secures-permit-for-new-yorks-largest-solar-project/
- hoodline.com/2026/09/steel-piling-rises-across-2-500-acres-in-genesee-county-for-ny-s-biggest-solar-farm/
- hecateenergy.com/case-studies/cider-solar/
Commercial operation date: None of the news or search results state a COD, so only the LBNL proposed COD of 2027-01-01 exists. Construction began in May 2025 and the capital stack closed in Feb 2026 ("final piece of the capital stack"), so 2027 is plausible but not independently confirmed.
Developer: LBNL and older news name Hecate Energy as developer. Greenbacker's announcement calls it "its Cider Solar Farm" and Greenbacker closed the tax equity financing, so it is the current owner. Hecate's case study says it developed and permitted the project and is managing construction.
Status: Greenbacker announced the start of major construction in May 2025, and Hoodline reported piling underway in Sept 2026. The LBNL IA status is stale relative to this.
About
Generated Apr 10, 2026 · Predates Sep 30, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
Cider Solar is a proposed 500 MW solar generation project located in Genesee County, New York. The developer is Hecate Energy Cider Solar LLC, and the interconnecting utility is NYPA. The project is in the NYISO interconnection queue as entry NYISO-811, with a queue entry date of April 3, 2019, and a proposed commercial operation date of January 1, 2027. Its interconnection status is currently at the System Impact Study phase.
The proposed project is linked to the existing Hecate Energy Cider Solar LLC operating plant (EIA ID 64163). Cider Solar has been the subject of recent news coverage, with 19 articles appearing in the press.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- NYISO queue source as of: Sep 30, 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NY
County
Genesee
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
Hecate Energy Cider Solar LLC
Utility
NYPA
Entity
NYISO
Service Type
—
Point of Interconnection
Dysinger - New Rochester 345kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- NYISO
- Trading Hub
- GENESE
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- 323607
- POI Substation
- MILLSEAT___LFGE
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Last updated 2026-03-26
View all 10 articlesObtain a complete list of Hecate Energy's operating assets, including in-service dates, to accurately identify plants added since 2023.
Structured data lookup for Hecate Energy with rankings and aggregations.
Solar queue pipeline by status
Data tables and metrics from the InfraSure database.
Hecate Grid Gwent Storage 1
Data-driven briefing on Hecate Energy — fleet, generation, financial, and news signals.
KCE NY 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.