Hilltop Solar
20 MW generation in Rensselaer, NY · In queue since March 2019 · Proposed COD May 2028
20 MW
Capacity
1
Components
Solar
7y 4m
In Queue
Facility Study
IA Phase
Signed Apr 2021
Queue → IA
2y 1m
IA → COD
7y 1m
Total Duration
2y 1m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2028-05-01
Hilltop Solar is a proposed 20 MW solar generation project located in Rensselaer County, New York. The project, developed by SunEast Hilltop Solar LLC, is interconnected within the New York Independent System Operator (NYISO) queue as project number NYISO-807, with an interconnection queue entry date of March 28, 2019. The proposed commercial operation date is May 1, 2028. Its interconnection status is currently in the Facility Study phase.
The project is linked to the existing SunEast Hilltop Solar Project operating plant (EIA ID 63868). Recent news coverage has discussed the development.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NY
County
Rensselaer
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
SunEast Hilltop Solar LLC
Utility
NM-NG
Entity
NYISO
Service Type
—
Point of Interconnection
Eastover - Schaghticoke 115kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- NYISO
- Trading Hub
- ZONE F
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about Hilltop SolarForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.