KCE NY 10
20 MW storage in Erie, NY · In queue since March 2019 · Proposed COD October 2026
20 MW
Capacity
1
Components
Battery
7y 8m
In Queue
Facility Study
IA Phase
Signed Oct 2022
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Queue → IA
3y 7m
IA → COD
4 years
Total Duration
3y 7m
Schedule
2 months past proposed COD
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Interconnection Queue; status 11
Project under construction
Typical: 6–18 months
Proposed COD: 2026-10-01
About
Generated Apr 10, 2026 · Predates Sep 30, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
KCE NY 10 is a proposed 20 MW battery storage project located in Erie County, New York. The developer is KCE NY 10, LLC. The project is interconnected to the New York Independent System Operator (NYISO) queue as entry NYISO-804, with a queue entry date of March 22, 2019. The proposed commercial operation date is October 1, 2026, and the project's interconnection agreement status is currently in the Facility Study phase.
The proposed project is linked to an existing operating facility, KCE NY 10, LLC (EIA ID 66682). The point of interconnection is the Erie Substation at 34.5kV. The project has appeared in recent news coverage.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- NYISO queue source as of: Sep 30, 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NY
County
Erie
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
KCE NY 10, LLC
Utility
NYSEG
Entity
NYISO
Service Type
—
Point of Interconnection
Erie Substation 34.5kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- NYISO
- Trading Hub
- WEST
- Hub Confidence
- MEDIUM
- Nearest Node (Estimated)
- 345030
- POI Substation
- PAVMNTRD_115_KV_BK1_REV_LBMP_A
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
KCE NY 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
KCE NY 31
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
KCE NY 21
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
KCE NY 30
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.