White Creek Solar
135 MW generation in Livingston, NY · In queue since November 2018 · Proposed COD June 2028
135 MW
Capacity
1
Components
Solar
8 years
In Queue
System Impact Study
IA Phase
COD target: 2028
One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.
Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.
Total Duration
9y 7m
Interconnection request submitted to ISO/RTO
Interconnection Queue; status 11
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-01
Cross-source intelligence
Experimental assessment saved at the research date. Predates the Sep 30, 2026 queue source. See the queue record for reported project facts.
Milestones in this assessment
Entered NYISO queue for System Impact Study
Research sources and reasoning (0 recorded sources)
low confidence at research time
No source list recorded with this assessment.
Commercial operation date: Only LBNL queue data available with proposed COD of June 2028. No independent news or press releases found to validate or contradict this target date.
Developer: Only LBNL filing entity available. No press releases or corporate announcements found to identify a parent operating company or confirm if this is a project-specific LLC versus an independent developer.
Status: LBNL shows Active status in System Impact Study phase as of queue filing. No news coverage found to indicate progression to later interconnection stages or construction activity.
About
Generated Apr 10, 2026 · Predates Sep 30, 2026 queue source
Figures and claims below reflect the saved summary. See the queue record for reported project facts.
White Creek Solar is a proposed 135 MW solar generation project located in Livingston County, New York. The project, developed by White Creek Solar, LLC, is in the New York Independent System Operator (NYISO) interconnection queue as queue ID NYISO-777. The project entered the queue on November 1, 2018, and has a proposed commercial operation date of November 1, 2027. Its interconnection status is currently in the System Impact Study phase.
The White Creek Solar project has been the subject of recent news coverage, with eight articles published in industry and regulatory news sources.
Summary provenance
Summary generated Apr 10, 2026 (UTC).
Source dates used by this summary were not recorded.
Dates in the current asset record
These may postdate the saved summary; they do not establish which inputs it used.
- NYISO queue source as of: Sep 30, 2026.
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NY
County
Livingston
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
White Creek Solar, LLC
Utility
RG&E
Entity
NYISO
Service Type
—
Point of Interconnection
Sta 82 - Sta 128 115kV
Data Source
LBNL + Live
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- NYISO
- Trading Hub
- ZONE B
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
KCE NY 2
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
KCE NY 31
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
KCE NY 21
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
KCE NY 30
Cross-dimensional entity briefing with KPIs, news intelligence, and fleet analysis.
Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.