White Creek Solar
135 MW generation in Livingston, NY · In queue since November 2018 · Proposed COD June 2028
135 MW
Capacity
1
Components
Solar
7y 8m
In Queue
System Impact Study
IA Phase
COD target: 2028
Total Duration
9y 7m
Interconnection request submitted to ISO/RTO
NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.
Typical: >42 months (historical); ~24 months target
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-06-01
Entered NYISO queue for System Impact Study
White Creek Solar is a proposed 135 MW solar generation project located in Livingston County, New York. The project, developed by White Creek Solar, LLC, is in the New York Independent System Operator (NYISO) interconnection queue as queue ID NYISO-777. The project entered the queue on November 1, 2018, and has a proposed commercial operation date of November 1, 2027. Its interconnection status is currently in the System Impact Study phase.
The White Creek Solar project has been the subject of recent news coverage, with eight articles published in industry and regulatory news sources.
Generated from interconnection queue and public data sources
Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.
See the full development-risk decomposition for this project.
State
NY
County
Livingston
Grid Region
NYISO (New York)
Market
ISO/RTO Member
Developer
White Creek Solar, LLC
Utility
RG&E
Entity
NYISO
Service Type
—
Point of Interconnection
Sta 82 - Sta 128 115kV
Data Source
LBNL
Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.
See the full risk decomposition + scenarios for this project.
Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.
See the full forecast + scenario decomposition for this project.
Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.
See the full revenue + DSCR projection for this project.
- ISO / RTO
- NYISO
- Trading Hub
- ZONE B
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No Ask reports yet for this entity.
Ask about White Creek SolarForward forecasts, scenario decomposition, and risk-decision tooling for this queue project.