Sunrise Wind (NYISO-766) — Project Summary

Queue ID
NYISO-766
Capacity
880 MW
Technology
Offshore Wind
Status
active
Location
Suffolk, NY
Region
NYISO
Developer
Sunrise Wind LLC
IA Status
System Impact Study

Sunrise Wind

NYISO-766BetaActiveOffshore WindNYISOLBNL

880 MW generation in Suffolk, NY · In queue since September 2018 · Proposed COD July 2027

BA: NYISISO/RTO: NYISONERC: NPCCRC: NYIS

880 MW

Capacity

1

Components

Offshore Wind

7y 10m

In Queue

System Impact Study

IA Phase

Signed Jan 2023

Status
Latest milestone45% complete · Q4 2024Fire Island News · 2026-02-28
Expected COD2026Power Technology · 2024-07-19
Delay reasonnational security concerns - work suspension orderFire Island News · 2026-02-28
Interconnection

Queue → IA

4y 4m

IA → COD

4y 6m

Total Duration

4y 4m

Construction25%
Queue EntrySep 28, 2018

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection AgreementJan 11, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 36–60 months

Commercial Operation

Proposed COD: 2027-07-01

Cross-source intelligence
Beta
High confidence·3 sources·as of 2026-06-01
Expected COD
2026
Queue date 1–2 years staleQueue: 2027-07-01
Developer
Ørsted
Filed as Sunrise Wind LLC
Status
Active
Active — construction 45% complete as of Feb 2026, proceeding after court order lifted Trump administration pause
Financing
Secured
Project financing secured prior to construction start; turbine supply contract with Siemens Gamesa awarded 2019 for 1.7 GW (includes this project)
Ownership history
  1. 2018·Deepwater Wind (original developer)Ørsted and Eversource joint venturesource
Key milestones
IA executedJan 11, 2023

System Impact Study phase initiated per NYISO

source
Permit approvedFeb 2026

US District Court order allowed project to proceed after Trump administration pause

source
constructionFeb 2026Most recent

Construction 45% complete, work resuming after regulatory clearance

source
Project lifecycle
as of 2026-02-28
PhaseConstructionThe Guardian · 2026-02-28
Phase history
2024-04Withdrawn2026-02Construction
OperationalNoThe Guardian · 2026-02-28
Technologyoffshore_windThe Guardian · 2026-02-28
DeveloperØrsted±The Guardian · 2026-02-28
DelayAnnouncedThe Guardian · 2026-02-28
Permit decisionGrantedThe Guardian · 2026-02-28
About

Sunrise Wind is a proposed 880 MW offshore wind generation project located in Suffolk County, New York. The project, developed by Sunrise Wind LLC, is interconnected to the NYISO grid under queue ID NYISO-766. The project entered the interconnection queue on September 28, 2018, and has a proposed commercial operation date of March 1, 2026. Its interconnection status is currently in the System Impact Study phase, and it will connect to the grid at Holbrook 138kV & West Bus 138kV.

The Sunrise Wind project has been the subject of recent news coverage, with 92 articles appearing in the press. These articles primarily focus on industry and development aspects of the project, with some coverage of regulatory and grid-related issues.

Generated from interconnection queue and public data sources

Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

NY

County

Suffolk

Grid Region

NYISO (New York)

Market

ISO/RTO Member

Developer

Sunrise Wind LLC

Utility

LIPA

Entity

NYISO

Service Type

Point of Interconnection

Holbrook 138kV & West Bus 138kV

Data Source

LBNL

DeveloperØrsted±Fire Island News · 2026-02-28
ApplicantØrsted±The Guardian · 2026-02-28
AgencyUS District Court / Department of Interior±The Guardian · 2026-02-28
RulingOrder±The Guardian · 2026-02-28
TransactionAcquisitionWindpower Engineering & Development · 2019-07-22
OfftakerØrsted and EversourceWindpower Engineering & Development · 2019-07-22
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
NYISO
Trading Hub
ZONE K
Hub Confidence
HIGH
Nearest Node (Estimated)
NGRID_A4_DSASP

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

Insights & Articles (10)Beta

Last updated 2026-03-26

View all 10 articles

No Ask reports yet for this entity.

Ask about Sunrise Wind
InfraSure platform

Forward forecasts, scenario decomposition, and risk-decision tooling for this queue project.