Sunrise Wind (NYISO-766) — Project Summary

Queue ID
NYISO-766
Capacity
880 MW
Technology
Offshore Wind
Status
active
Location
Suffolk, NY
Region
NYISO
Developer
Sunrise Wind LLC
IA Status
System Impact Study

Sunrise Wind

NYISO-766BetaActiveOffshore WindNYISOLBNL + Live

880 MW generation in Suffolk, NY · In queue since September 2018 · Proposed COD July 2027

BA: NYISISO/RTO: NYISONERC: NPCCRC: NYIS

880 MW

Capacity

1

Components

Offshore Wind

8y 2m

In Queue

System Impact Study

IA Phase

Signed Jan 2023

Asset Intelligence Map

One connected view of the asset's ownership, operating or development evidence, grid context, commercial relationships, history, and forward outlook.

5 live dimensions
4 decision models

Expand a branch, then select a fact to jump to its full section. Locked leaves open a contextual request.

Structured from the current asset record; empty data branches are omitted.Locked nodes are InfraSure decision models; no simulated values shown.
Interconnection

Queue → IA

4y 4m

IA → COD

4y 6m

Total Duration

4y 4m

Construction25%
Queue EntrySep 28, 2018

Interconnection request submitted to ISO/RTO

TCS Study

NYISO transitioned to a Transitional Cluster Study (TCS) format in 2024.

Typical: >42 months (historical); ~24 months target

Interconnection AgreementJan 11, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Interconnection Queue; status 12

Project under construction

Typical: 36–60 months

Commercial Operation

Proposed COD: 2027-07-01

News-reported activity

From dated articles. These observations may describe earlier stages or other project phases; see the queue record above for reported filing status.

Project statusUnder constructionPOWER Magazine · 2020-10-28
Latest milestonefirst power · Q4 2024New Hampshire Public Radio · 2026-03-26
Expected COD2026Power Technology · 2024-07-19
Delay reasonpermitting delays due to COVID-19 pandemic and BOEM regulatory processPOWER Magazine · 2020-04-30

Cross-source intelligence

Saved research · Beta
Researched Oct 25, 2026

Experimental assessment saved at the research date. See the queue record for reported project facts.

Research COD
2027
Developer in saved assessment
Ørsted
Filed as Sunrise Wind LLC
Status at research time
Construction
LBNL shows 'active' with a stale System Impact Study IA status. In reality the project is under offshore construction, with about 20 turbines installed and the project now cited at 924 MW (LBNL lists 880 MW). It faces federal political and legal headwinds but is proceeding toward 2027.
Financing
Not recorded

Milestones in this assessment

COD target2027Latest in this assessment

Ørsted states Sunrise Wind (924 MW) is expected to be operating in 2027.

sunrisewindny.com
Research sources and reasoning (6 recorded sources)

high confidence at research time

  1. sunrisewindny.com/about-sunrise-wind
  2. sunrisewindny.com/
  3. patch.com/new-york/shirley-mastic/924-megawatt-sunrise-wind-farm-shirley-coast-making-good-progress-official
  4. newsday.com/long-island/environment/sunrise-empire-wind-wurqm2w1
  5. en.wikipedia.org/wiki/Sunrise_Wind
  6. power-technology.com/projects/sunrise-wind-project-new-york/

Commercial operation date: Ørsted's project site says Sunrise Wind "is expected to be operating in 2027", Patch reports the project "is slated to be complete in 2027, Ørsted says", and Newsday says backers expect it to be fully operational next year. This matches the LBNL proposed COD of 2027-07-01, so only the year is stated.

Developer: The LBNL filing entity, Sunrise Wind LLC, is the project company. The Ørsted-branded project site lists it at its address, and Power Technology names Ørsted as developer. No ownership change is documented in the provided sources.

Status: Patch, Wikipedia and the Ørsted project site all describe Sunrise Wind as under construction. Newsday reports it pressing forward despite Trump administration resistance.

Project lifecycle
as of 2026-03-26
PhaseOnlineNew Hampshire Public Radio · 2026-03-26
Phase history
2024-04Withdrawn2026-01Construction2026-03Online
OperationalNo±The Guardian · 2026-02-28
Technologyoffshore_windNew Hampshire Public Radio · 2026-03-26
DeveloperØrsted±The Guardian · 2026-02-28
COD achievedReportedNew Hampshire Public Radio · 2026-03-26
Permit decisionContestedNew Hampshire Public Radio · 2026-03-26

About

Saved background

Generated Apr 10, 2026 · Predates Sep 30, 2026 queue source

Figures and claims below reflect the saved summary. See the queue record for reported project facts.

Sunrise Wind is a proposed 880 MW offshore wind generation project located in Suffolk County, New York. The project, developed by Sunrise Wind LLC, is interconnected to the NYISO grid under queue ID NYISO-766. The project entered the interconnection queue on September 28, 2018, and has a proposed commercial operation date of March 1, 2026. Its interconnection status is currently in the System Impact Study phase, and it will connect to the grid at Holbrook 138kV & West Bus 138kV.

The Sunrise Wind project has been the subject of recent news coverage, with 92 articles appearing in the press. These articles primarily focus on industry and development aspects of the project, with some coverage of regulatory and grid-related issues.

Summary provenance

Summary generated Apr 10, 2026 (UTC).

Source dates used by this summary were not recorded.

Dates in the current asset record

These may postdate the saved summary; they do not establish which inputs it used.

  • NYISO queue source as of: Sep 30, 2026.
Development Risk

Realization risk before commercial operation — cluster-study clearance, IA timing, counterparty mix, and withdrawal probability vs cohort. The diligence view that determines whether this project is worth pursuing. Powered by InfraSure's development-stage modeling stack.

Available on the InfraSure platform

See the full development-risk decomposition for this project.

P(COD by stated date)
Withdrawal probability vs cohort
IA cluster risk
Project Details

State

NY

County

Suffolk

Grid Region

NYISO (New York)

Market

ISO/RTO Member

Developer

Sunrise Wind LLC

Utility

LIPA

Entity

NYISO

Service Type

—

Point of Interconnection

Holbrook 138kV & West Bus 138kV

Data Source

LBNL + Live

DeveloperOrsted±Power Technology · 2024-07-19
ApplicantØrsted±The Guardian · 2026-02-28
AgencyUS District Court / Department of Interior±The Guardian · 2026-02-28
RulingOrder±The Guardian · 2026-02-28
TransactionAcquisitionWindpower Engineering & Development · 2019-07-22
OfftakerØrsted and EversourceWindpower Engineering & Development · 2019-07-22
Risk Analytics

Composite operating-phase risk view — what this asset's risk profile would look like once it reaches commercial operation. Climate hazards across its operating life, expected generation variability, and offtake counterparty exposure, decomposed into a single decision-grade score. Powered by InfraRisk.

Available on the InfraSure platform

See the full risk decomposition + scenarios for this project.

Climate hazards (8+)
Generation variability (P10/P50/P90)
Offtake + transmission counterparty
Generation Forecast

Forward generation outlook — what this project would produce assuming it reaches commercial operation. Probabilistic ranges (P10/P50/P90) across weather, demand, and policy scenarios, conditioned on the proposed COD. Powered by InfraSure's generation modeling stack.

Available on the InfraSure platform

See the full forecast + scenario decomposition for this project.

P50 conditioned on COD
Capacity factor vs cohort
Weather + policy scenarios
Financial Forecast

Forward revenue, DSCR projection, and financing-close risk — conditioned on commercial operation. The bankability view that determines whether the deal clears its covenants once online. Powered by InfraSure's asset cashflow stack.

Available on the InfraSure platform

See the full revenue + DSCR projection for this project.

Revenue conditioned on COD
Financing close risk
Cohort DSCR comparison
Market Context
Approximate
ISO / RTO
NYISO
Trading Hub
ZONE K
Hub Confidence
HIGH
Nearest Node (Estimated)
NGRID_A4_DSASP

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.